|| High Country Press Newswire

OCTOBER 29, 2009 ISSUE

NCDOT Announces Plan to Begin Clean up of I-40 Rockslide

Interstate Could Be Closed for Three Months

Interstate 40 could be closed for more than three months between Exit 20 in North Carolina and Exit 451 in Tennessee because of a rockslide that occurred last Sunday, October 25. NCDOT crews are currently on site clearing debris. NCDOT, a contractor and a rock stabilization specialist announced a three-phase, three-month plan this week to restore traffic flow on the heavily traveled thoroughfare. More info is available on page 9-A. Photo courtesy of NCDOT

The N.C. Department of Transportation has established a plan to begin cleaning up and stabilizing the area where a rockslide occurred on I-40 on Sunday, October 25. The interstate is closed at Exit 20 in North Carolina and at Exit 451 in Tennessee.  

Because of the challenging terrain where the slide occurred—steep mountain on one side and river on the other—NCDOT, along with rock stabilization specialist Janod Contractors of Champion, N.Y., and contractor Phillips & Jordan Inc. out of Knoxville, Tenn. and Robbinsville, have developed a three-phased plan: 

Phase 1
-Rock in the lower and middle sections of the slide that is still unstable will be removed.
-Large boulders that fell will be blasted into smaller pieces. 

Phase 2
-The rocks removed from the side of the mountain and the pieces of blasted boulders will be used to construct a ramp that will enable specialty equipment to climb to the top of the slide area using a pulley system. Specialty equipment is en route from New York for use in the clean up.  

Phase 3
-Crews will begin removing rock from the top down to the bottom and begin stabilizing the slope. This work involves chiseling off rock—on a smaller scale, this is like using a hammer and pry bar—and blasting to stabilize the area. As crews work down the slope, experts will analyze each boulder to determine whether it is secure or should be removed. The area above the top of the slide will also be stabilized. 

Once all debris is cleared, temporary asphalt will be laid on the highway so that traffic can be restored until permanent asphalt can be laid in the spring.

The slide is about 150 feet high and 200 to 300 feet wide and the majority of debris is rock. Because of safety concerns while work is taking place, travel lanes will likely not open until all work is completed, which is expected to take about three months. Estimated cost is $2 million to $10 million. Time and cost estimates will be revised throughout the work.

Gov. Beverly Perdue is expected to make an emergency declaration, which will enable the state to ask the Federal Highway Administration for federal funding. 

Geotechnical scientists and engineers do not know the exact cause of the slide, but are looking at several potential factors, including possible tremors, or freezing and thawing of water in cracks in a wedge in the slope, causing expansion and contraction of the rock plates.
 
Travelers can still reach Western North Carolina via a number of routes. An official detour has been set up for inter-state traffic. Motorists traveling west to Tennessee should take I-40 West to I-240 West (Exit 53B) in Asheville to I-26 West (Exit 4A). Follow I-26 West from Asheville to I-81 South (Exit 8A) in Tennessee, back to I-40. Eastbound motorists will follow the reverse directions. (See map)


THE HIGH COUNTRY PRESS TEAM

Email Ken

KEN KETCHIE

Editor | Publisher | Ringleader
info@highcountrypress.com
Email Sam

SAM CALHOUN

Managing Editor
sam@highcountrypress.com
Email Anna

ANNA OAKES

Entertainment Editor
anna@highcountrypress.com
Email Corinne

CORINNE SAUNDERS

Staff Writer
corinne@highcountrypress.com
Email Heather

HEATHER HENDRICKS

Classifieds | Office Manager
classifieds@highcountrypress.com
Email Laila

LAILA PATRICK

Finance Manager
laila@highcountrypress.com
Email Beverly

BEVERLY GILES

Sales Manager
bev@highcountrypress.com
Email Bryan

BRYAN McGUIRE

Sales Representative
bryan@highcountrypress.com
Email Jamie

JAMIE CARROLL

Web - Admin | Designer | Monkey
jamiec@highcountrypress.com
Email Courtney

COURTNEY COOPER

Creative Director
courtney@highcountrypress.com
Email Michelle

MICHELLE BAILEY

Production Manager
ads@highcountrypress.com
Email Tim

TIM SALT

Graphic Artist | Intl. Bass Master
salt@highcountrypress.com
Email Patrick

PATRICK PITZER

Graphic Artist
patrick@highcountrypress.com
Email Kenneth

KENNETH DANCY

Distribution Manager
info@highcountrypress.com
Email Dan

DANIEL KAPLE

Distribution Monkey
daniel@highcountrypress.com

FOLLOW US ON TWITTER

SUBSCRIBE TO OUR NEWSLETTER